Please enjoy this 15 second time lapse of October which is month number one our of ten.
Monday, November 13, 2017
Tuesday, October 17, 2017
Rough in
The crews are busy 'roughing in' the underground plumbing piping for all the toilets. This has to be done before the slab is poured.
Wednesday, October 11, 2017
Footers
The first concrete for the building has been poured. Today the concrete footers for the building columns were poured into place. At the end of the day, the work will break for the holidays of Shemini Atzeres and Simchas Torah and then resume, GD willing, full force on Monday
Sunday, October 8, 2017
Monday, September 25, 2017
Monday, September 18, 2017
Action time!
During the last year we have did extensive work on the site. As you can see from the 'before and after' pictures below, the entire property was graded, utilities were installed, storm water management systems were put in place, and the pad was readied for the new building.
At long last the construction of the building has now gotten underway. We plan to bring you, on this blog, ongoing updates and pictures of the construction project.
Before
At long last the construction of the building has now gotten underway. We plan to bring you, on this blog, ongoing updates and pictures of the construction project.
Before
After